Aberdeen FC this evening announced that they have reached a major milestone with the development of their training complex at Kingsford.

The concrete floor of the Pavilion building has been completed, thanks to the recent mild winter weather.

Raymond Edgar, the club’s Project Director told the club website:  “The completion of this section means that future progress of the structure is less weather dependant. Once the concrete has cured this will allow the erection of the timber frame structure which is programmed for mid-March, meaning that the pavilion remains on programme for completion late summer this year.”